When Business Access Was Blocked

Last reviewed: June 24, 2026

The Scenario

A curb-lane project occupied the frontage of several businesses, blocking a driveway and the parking those businesses relied on, without a plan to maintain access during the work.

The Compliance Issue

Work in the right-of-way affects adjacent property and business access. Blocking a driveway or required parking without a plan creates complaints and can conflict with permit conditions.

How It Surfaced

The affected businesses raised complaints, and the lack of maintained access was noted against the permit conditions.

How It Was Resolved

Access was restored — the driveway kept usable and coordination arranged for deliveries and parking — and the staging was adjusted to preserve access through the work.

How to Prevent It Upstream

Property and business access is identified in planning, and the staging and closures are arranged to maintain driveways, deliveries, and required parking, coordinating with affected businesses in advance.

Lessons

  • Right-of-way work has to account for adjacent access.
  • Driveways, deliveries, and parking are planned, not improvised.
  • Early coordination with businesses prevents complaints and conflicts.